At a glance: Kruševac · Follower city · KSV1, KSV2 · Bus information system: specifications being defined; Brianova Street: planning and baseline data (as of May 2026) · Sources: D6.3, D3.6
Overview
Kruševac is a regional centre in central Serbia with a semi-urban character. Public transport carries only 14% of trips, and the city wants to make it more attractive and improve conditions for walking and cycling in the centre. It has earlier experience with participatory mobility planning and tactical urbanism.
Both interventions follow the city's Sustainable Urban Mobility Plan. Partners include the public transport operator Yugo Prevoz, disability associations, schools, local businesses, civic associations and a cycling association.
Highlights
Code | Intervention | Status (May 2026) | Planned budget |
|---|---|---|---|
KSV1 | Real-time bus information at 4 stops | Specifications being defined | €75,000 |
KSV2 | Brianova Street redesigned as a shared space | Planning and baseline data | about €180,000 |

Real-time bus information (KSV1). Digital boards at 4 bus stops in the centre, GPS units on buses, a control centre and a route-planner app, with Serbian and Cyrillic interfaces. Budget: €22,500 for on-board units, €21,000 for the boards, €15,300 for the control centre with five years of maintenance and €16,200 for the app.
Brianova Street (KSV2). A key walking and cycling route in the centre will become a shared space, with speed humps, raised crossings, a narrower roadway, wider paths, lowered kerbs, furniture and planting, but no separate bike lanes. Budget: €15,000 for design, €100,000 for construction, €30,000 for furniture, €20,000 for landscaping and €15,000 for signs and traffic calming.
Inspired by. Helsinki's data work, Milan's decision support and tactical urbanism, Copenhagen's street design and Zaragoza's pedestrian areas and stakeholder engagement.
Who was involved. Workshops and dialogues with disabled and visually impaired people during planning, and awareness-raising activities.
Practical relevance
Use a detailed budget. Kruševac's itemised costs give other cities a realistic starting point for similar projects.
Expect the timeline to stretch. The 2025 plan aimed for full deployment of the bus information by May 2026 and street works from February 2026; by May 2026 both were still in preparation.
Prepare for business concerns. The city identified resistance from local shops, worried about losing customers, as a main risk for the street redesign.
Publication details
Based on ELABORATOR deliverable D6.3, Follower Cities Final Implementation Report (Work Package 6, July 2026), edited by Juraj L. Vertlberg and Sanja Ševrović (FPZ), status as of May 2026. Budget, plans and inspirations: D3.6, Twinning inception, replication plans and technical definitions of the Follower cities interventions (May 2025, revised August 2025), edited by Marko Ševrović with Shanna Lucchesi (EIRA). Both public.