How to write a replication plan

Methodology

Training

Intervention

Tool

Data

Study

Use case

THINGS, based on D3.6 by EIRA and the Follower cities

Overview

A replication plan sets out how your city will adapt an intervention that was tested somewhere else. ELABORATOR's six Follower cities wrote one for each of their nine interventions in 2025. In the project's words, replication is "not merely about copying what works".


Highlights

The nine sections

  1. Selected intervention: what you will do, and which intervention elsewhere inspired it

  2. Replicability potential: how it fits your Sustainable Urban Mobility Plan, what you will adapt locally, and the steps to replicate it

  3. Detailed description: technical requirements and key points to watch during implementation

  4. Governance: who is involved and their roles

  5. Legal framework: which rules and approvals apply

  6. Budget

  7. Timeline, with milestones

  8. Monitoring and evaluation: how you will track progress and which data you will collect

  9. Risks and how to reduce them

Example: Ioannina's shared e-bikes

Ioannina, in Greece, planned its first municipal shared e-bike system.

Section

Ioannina's plan (2025)

Inspired by

Issy-les-Moulineaux, Copenhagen, Helsinki and Trikala

Description

3 docking stations with 10 bays each, 14 e-bikes and a smart platform

Adaptations

Local weather and the cost of use

Governance

11 stakeholders, including the regional union of disabled people, a local cycling group and the urban bus association

Legal framework

No local rules existed, so a municipal micromobility regulation was needed

Budget

Equipment €30,000; installation and maintenance €76,000; software €64,000

Timeline

Regulation by May 2025; equipment tender by June 2025; software by August 2025

Risks

Regulation delayed; procurement delayed; low use. Responses: broad consultation, starting early, alternative suppliers, information campaigns

As of May 2026 (D6.3), Ioannina had its rules, sites and tender documents ready; procurement was the next step.


Practical relevance

Use the nine sections as a checklist before you commit to an intervention seen in another city. The Follower cities found these points most important: early involvement of stakeholders, clear rules, continuous communication and solid monitoring. They also stressed that governance, cooperation and the capacity of the city administration matter as much as the technical solution. The Ioannina example shows that the legal framework and procurement can take longer than the original timeline.


Publication details

Based on ELABORATOR deliverable D3.6, Twinning inception, replication plans and technical definitions of the Follower cities interventions (Work Package 3, May 2025, revised August 2025), edited by Marko Ševrović with Shanna Lucchesi (EIRA) and the Follower cities. Ioannina's status: D6.3, Follower Cities Final Implementation Report (July 2026, FPZ). Both public.


Related


Disclaimer: The content of this article may be updated or changed, and this page will be updated if it does.

Full materials

Share this page:

Stay in touch!

Sign up to our mailing list to receive exclusive access to our newsletter and stay up to date with the latest project news and events.

Thanks for submitting!

Elaborator logo
  • LinkedIn
  • X

© 2023 Elaborator

Crafted with ♥️ by Threerooms

Co-funded EU logo

Funded by the European Union. Views and opinions expressed are however those of the author(s) only and do not necessarily reflect those of the European Union or CINEA. Neither the European Union nor the granting authority can be held responsible for them.

Civitas-Logo
EU-Mission-Logo

ELABORATOR is part of the CIVITAS Initiative and contributes to the goals of the EU Mission: Climate-Neutral and Smart Cities