At a glance: Issy-les-Moulineaux · Lighthouse city · ISSY1, ISSY2, ISSY3 · Light-emitting cycle marking operational since December 2024; mobility observatory supplying data (October 2026); GECO AIR app tested internally · Sources: D5.2, D3.5, D5.4
Overview
The Living Lab is in Issy Val de Seine, the economic centre of Issy-les-Moulineaux and one of the innovation hubs of the Greater Paris area. Around 70,000 people come to the city each day, doubling its population.
The municipality aims to be climate neutral by 2050 and has set annual objectives in a climate budget since 2021. It is also restructuring its major roads and urban spaces through the Axes de vie project. In ELABORATOR, the city worked with Issy Média, Colas, IFPEN and Urban Radar.
Highlights
Code | Intervention | Status |
|---|---|---|
ISSY1 | Light-emitting road marking that warns drivers of cyclists at a junction | Operational since December 2024; second phase since March 2026; evaluation ongoing (July 2026) |
ISSY2 | Mobility observatory for safety, carbon footprint and inclusivity | Supplying data used in D5.4 (October 2026) |
ISSY3 | GECO AIR app that estimates trip emissions and encourages active travel | Internal test completed; company challenges planned (July 2026) |

Light-emitting marking (ISSY1). At this junction, right-turning vehicles, especially trucks, have large blind spots for cyclists. Colas installed LED tiles in the road. From December 2024 to March 2026 they lit up when the traffic light was green; since March 2026 they light up only when a cyclist is detected, to avoid drivers getting used to them. Approval took more than 7 months: the national road safety agency validated the file in November 2024, and the road is regional, so the Département des Hauts-de-Seine also had to agree.
Mobility observatory (ISSY2). Three sensors have been installed since the start of the project: a camera at the road-marking site and two citizen-science sensors from IAAC, one at the town hall and one carried by a resident on his commute. D5.4 used traffic counts from the city's monitoring system at four locations (6 May 2026).
GECO AIR (ISSY3). The free IFPEN app was promoted locally and tested inside Issy Média and the city first. The test found bugs and led to a simpler interface before opening the app to citizens.
Modelled (D5.4). A stress test of the road network found Rue du Général Leclerc and Boulevard Gambetta to be the most critical corridors if disrupted.
Practical relevance
Find the right people to talk to early. National and regional approvals can take many months, especially on roads the city does not manage.
Ask cyclists' associations. They have excellent knowledge of where cyclists are at risk.
Set a direct line with the supplier. A dedicated channel between Colas and the city helped spot problems faster.
Give a data observatory clear objectives from the start, and treat the road department staff as experts to keep them engaged.
Test apps internally before launch.
Publication details
Based on the Issy-les-Moulineaux chapter of ELABORATOR deliverable D5.2, Lighthouse Cities Implementation Final Report (Work Package 5, July 2026), edited by Merja Penttinen, Anu Tuominen and Johannes Mesimäki (VTT), with contributions from the Lighthouse city partners. Intervention definitions: D3.5, Technical definitions of the Lighthouse cities interventions – version II (May 2025), edited by MCRIT. Network analysis: D5.4, Lighthouse Cities Interventions Validation (October 2026), edited by Alexandros Liazos (ICCS). All public.